Project Details
- Category: Cellular Infrastructure RolloutWireless Solutions
- Client: Zain Iraq
- Location: Iraq
- Year Of Completed: 2017
This project involved the rapid delivery of 5 Cell on Wheels (COWs) units, each featuring a 30-meter deployable mast, to support fast and flexible mobile network coverage for Zain Iraq.
MOSECO was responsible for the complete supply, assembly, configuration, and commissioning of the COWs units, successfully delivering fully operational systems within an accelerated two-week timeframe. The deployment enabled Zain Iraq to quickly enhance coverage and capacity in response to dynamic network demands and temporary coverage requirements.
Supply of 5 Cell on Wheels units with 30m deployable masts
Mechanical assembly and structural configuration
Compliance with telecom and safety standards for mobile deployment
Integration of dual generators per COW for power redundancy
Main Distribution Boards (MDBs) and power controllers
Load management and protection for continuous operation
Installation of telecom cabinets and Radio Base Stations (RBS)
Integration of up to 9 antennas per COW
Grounding, cabling, and RF readiness
System configuration and functional testing
Verification of power, RF, and control performance
Delivery of fully operational, ready-to-deploy COWs
Delivery of 5 fully operational COWs within 2 weeks
Rapid enhancement of mobile network coverage and capacity
High availability and reliability in temporary deployments
Increased operator flexibility for emergency and event coverage
This project further demonstrates MOSECO’s strength in fast-track mobile infrastructure deployments, combining engineering precision with accelerated execution.
By delivering fully integrated and rapidly deployable COWs solutions, MOSECO enabled Zain Iraq to respond swiftly to network demands while maintaining high service quality.